Tollways completion pushed back

- Advertisement -

Target completion of three major expressway projects has been moved to 2022 up to 2023.
Metro Pacific Investment Corp. (MPIC) in a report as of March 19, 2021 said the P30.5-billion Cebu Cordoba link expressway (CCLEX) project and the P19.6-billion NLEX-SLEX connector road project will be completed in 2022.

The construction works for CCLEX and the NLEX-SLEX connector road section 1 is ongoing while pre-construction on the connector road for section 2 started, according to MPIC. The right- of-way (ROW) is 100 percent available for the Caloocan segment and 74 percent for the Manila segment.

Full completion of the P52.9-billion Cavite-Laguna Expressway is moved from 2022 to 2023, with ROW for Laguna segment now 67 percent available and Cavite, 92 percent.