Light Rail Manila Corp. (LRMC) is set to implement a three-month temporary lane closure of Manila Cavite expressway (Cavitex) as part of constructions works for the 11-7 kilometer Light Rail Transit line 1 (LRT-1) Cavite extension project.
In a statement, LRMC said the temporary lane closure of the southbound lane of Cavitex near Paranaque bridge is scheduled from September 15 until December 15 to give way to the pipe relocation works by a water concessionaire required for the construction in the area relative to the LRT-1 Cavite extension.
This is a follow-through of the test pit works (bridge and pipe inspection) which was conducted in the same area last May 2020.
Since the start of the civil works in September 2019, LRMC said that percentage completion rate has reached 40 percent for the project aspects within LRMC’s scope.